Start with the exact UPS, not a nominal battery label
A 192V, 384V or 512V label is only a platform direction. The complete battery operating range must fit the UPS DC input range, charging behavior and low-battery settings before a configuration can be reviewed.
Record the UPS brand, exact model and topology. The manual, nameplate, battery-setting pages and existing battery circuit provide stronger evidence than a capacity label alone.
- UPS brand and exact model
- UPS topology and rated capacity
- Input and output phase and voltage
- DC voltage window
- Minimum DC operating voltage and low-battery shutdown threshold
- Center-tap or two-wire full-bus arrangement
Separate actual load from UPS rated capacity
Battery selection must use the actual critical load in kW. Two UPS systems with the same kVA rating may support very different loads and therefore require different current and energy from the battery.
Define whether the project needs generator bridging, controlled shutdown or longer operation. A 15-minute high-power duty and a 60-minute energy duty require different power and energy design logic.
- Actual critical load in kW
- UPS kVA and kW rating for reference
- Required backup time and operating objective
- Expected load growth and design margin
- Redundancy and parallel-operation objective
With the actual load, required runtime and UPS DC bus collected, review the preliminary battery requirement before selecting a configuration.
Use the UPS High-Voltage Lithium Battery PlannerCheck charging limits and recovery after discharge
The UPS charger is part of the battery system. Confirm normal charging voltage, maximum charging voltage and the available charge-current limit before selecting module quantity or energy capacity.
Charge-current limit affects recharge time. This is especially important for extended-runtime projects and sites with repeated outages before the battery has fully recovered.
- Normal and maximum charging voltage
- Charge-current limit
- Lead-acid float or equalize control on retrofit projects
- Required recharge time
- Restart behavior after BMS cut-off or complete battery shutdown
Define BMS, protection and communication behavior
A physical CAN or RS485 connector does not by itself confirm UPS protocol compatibility. The protocol, messages, alarms, cut-off logic and control responsibility must be reviewed for the exact project.
The BMS, breaker, contactor, fuse, cable and UPS battery input form one DC protection path. Confirm how alarms, isolation and recovery are handled locally.
- BMS current level and cut-off settings
- Required CAN, RS485, dry-contact or network protocol
- Contactor, breaker and fuse arrangement
- Emergency isolation and pre-charge requirements
- Alarm, shutdown and restart behavior
Use approved discharge data for runtime
Do not use a fixed 10-, 15- or 30-minute runtime claim without an approved constant-power discharge curve for the exact battery model, current level, end voltage and temperature.
Runtime review should include minimum UPS DC voltage, UPS efficiency, battery and BMS cut-off, site temperature, state of charge and the project margin. Preliminary nominal energy is not a runtime guarantee.
- Approved constant-power discharge curve
- Specified end voltage
- Specified temperature and current level
- UPS efficiency and minimum DC input
- Battery state-of-charge and design margin
Review cabinet, access and site conditions
A technically suitable battery still needs a workable installation path. Cabinet arrangement, maintenance space, floor loading and cable route should be reviewed before final dimensions and weight are accepted.
Site temperature, ventilation, access and local fire requirements affect the final project configuration. Fire-protection scope is configuration-dependent and must not be assumed from a product-family page.
- Installation location and ambient temperature
- Floor loading and maintenance clearance
- Cable route and distance to the UPS
- Equipment access route
- Cabinet or rack arrangement
- Local fire requirements
Confirm certification and project responsibility
Certification scope, shipping documentation and applicable standards are confirmed according to the selected model and destination. A general platform statement is not evidence for every cabinet or project.
Define who is responsible for local design, installation, commissioning, code compliance and ongoing service before the order is finalized.
- Destination country and certification scope
- Required shipping and technical documents
- Local installation and commissioning responsibility
- Warranty and service expectations
- OEM, ZYKEVO or neutral-label presentation
Information to send before quotation
A useful preliminary RFQ combines the electrical evidence, duty, site and commercial scope. Missing information can be identified during review, but no final compatibility or runtime commitment should be made until the critical inputs are confirmed.
- UPS brand, exact model, topology and rated capacity
- DC operating window, minimum DC voltage and charging information
- Existing battery quantity, arrangement and center-tap/full-bus structure
- Actual critical load in kW and required backup time
- BMS communication and protection requirements
- Cabinet, site, destination, certification and labeling scope
Related project paths
- Review the high-voltage LiFePO4 battery product range
- Explore the 192V LiFePO4 battery platform
- Explore the 384V LiFePO4 battery platform
- Explore the 512V LiFePO4 battery platform
- Collect the UPS DC bus evidence before selecting a battery
- Confirm CAN and RS485 protocol requirements before final matching
- Prepare the high-voltage lithium battery checklist
- Send Your Requirement